1. The operation of the substation must be carried out in accordance with the relevant regulations of the electrical sector, and the corresponding safety measures should be taken in the order specified in the regulations.
2. The switching operation must be carried out according to the electrical work ticket issued by the supervisor or the notice of the competent department.
3. The switching operation must be carried out by 2 persons. Among them, the positive value is the guardian and the deputy is the operator. The complicated and important switching operation should be supervised by the supervisor.
4. Operating procedures:
Preparation: The manager will explain the contents of the work. The foreman of the class will fill in the “Trip Operation Ticket” according to the work content, or make a record on the “Distribution Room Maintenance Record”.
Operation mode and requirements: (1) When the maintenance and cleaning of the whole low-voltage cabinet is carried out, the "Turn-off operation ticket" should be filled in, and it should be recorded in the "Current Value Record" of the "Duty Record Book". Record on the room maintenance record. (2) It should be clearly recorded in the operation record of the “Working Recorder” when doing local power transmission. Stop the grid that affects the normal household electricity consumption, first notify the company's leaders, and after approval, notify the relevant households three working days in advance.
5. All electrical equipment that has been put into the system, whether or not there is electricity at that time, should be regarded as live equipment. It is necessary to go through the power-off procedure before touching the live part.
6. The power outage procedure is handled according to the following regulations:
7. On the 10 kV electrical equipment or the busbar part directly connected to the low-voltage line of the transformer, the dispatched person in charge shall fill in the blackout ticket and go through the formalities with the person in charge of the work and the person in charge of the transformer room;
8. In the part of the trunk line of 220 volts and above, the person in charge of the dispatched work shall fill in the blackout ticket, and the person in charge of the work shall send it to the person in charge of the transformer room to go through the formalities;
Part of the work of 9, 220 volts and above, after the person in charge of the work obtains the consent of the relevant personnel, cut off the relevant power supply and hang the power card at the disconnection point;
10. When the transformer room needs to be powered off on duty, the special power-off card will be hung at the disconnection point of the power-off equipment, and the card-handling person in charge will be accepted;
11. When the household isolating switch and previous work, the mains of the transformer room shall go through the power outage procedure to the power supply bureau in accordance with relevant regulations.
12. A person in charge of work can only apply for one power outage ticket at a time.
13. After receiving the power outage ticket, the person in charge of the transformer room should do the following work;
13.1 The staff of the working group shall confess the safety measures on the site of the power outage, the scope of the permit work, and the surrounding live parts.
13.2 If there is a live part around the power outage site, special guardianship shall be designated;
13.3 It is not allowed to work alone in a partially de-energized high-voltage room or transformer room.
14. Fill in the security measures for the power outage ticket;
15. Fill in the operation ticket for the switch, operate by the attendant, and take safety measures;
16. The person in charge of the escort will go to the scene of the power outage to check the safety measures, and verify the power outage equipment with the electroscope. The certificate clarifies that there is no electricity;
17. Responsible for the location of the surrounding live equipment and precautions for the person in charge of the work;
18. If there is a live part around the power outage site, special person supervision should be appointed; when the work person in charge signs the work permit of the power outage ticket, the work permit is torn off and handed over to the person in charge of work, and the work is started.
19, 10 kV equipment in the visible range without obvious disconnection point, you need to install the grounding line, the duty officer is responsible, and recorded in the safety measures column. When working on the overhead line, the grounding line is required to be installed by the person in charge of the work. In the safety measures column, indicate "self-installation". Who installed the grounding wire and who dismantled it.
20. After all the work is completed, the staff member should clear the site to restore the power-off equipment to the power-sending state, evacuate all the staff members from the scene, and then fill out the power-off ticket cancellation column, and work with the work permit to change the electricity room supervisor to go through the cancellation procedures, and inform All staff, after which the equipment is considered to be live and must not be touched or approached.
21. After receiving the cancellation notice, the supervisor of the transformer room will cancel all safety measures and sign the cancellation of the power-off ticket after checking the work permit (supervisor).
22. On the same line, there are two groups working independently at the same time, and the power failure procedures must be handled separately.
23. In the event of an emergency, you may not need to operate the ticket, but you must cut off all relevant power sources, hang up the power card at the disconnected county, do the necessary safety measures and have someone to guard. After the event, the duty record should be made and reported to the supervisor.
When the emergency is handled, you may not go through the power outage.
24, where the county hangs the electrical equipment of the power card, is not allowed to close the power transmission, has not written off the power outages, the power card is not allowed to pick up.
25. The blackout ticket should be filled in with a pen and must not be altered. The blackout ticket that has been cancelled should be properly kept and handed over to the direct jurisdiction for future reference.
Related Forms "Switching Stop, Power Transmission Operation Ticket"

Medical Cable Assembly

We can follow customers' drawings or design to make Customized wire harness for various industries: game machine, ATM, POS machine, etc.

Customized wire assembly with AVL components from original manufactures. Also harness with local equivalent componets are workable with short L/T and competitive price, also flexible MOQ.

Medical Wire Assemblies,Medical Alligator Clip Cable,Medical Cable Assembly,Medical Wire Harness,Medical Cable

ETOP WIREHARNESS LIMITED , https://www.wireharnessetop.com

Posted on